Shengli Oilfield Ocean Drilling opens up new markets

2017-02-20

Shandong International online news channel (Wang Zhenglu correspondent Liu Shoujiang): February 15, the Offshore drilling company manager Zhang Jinlong of Sinopec Shengli Petroleum Engineering Co., Ltd. and the vice president Zhao Hui of CIMC Raffles, as representatives of both sides, signed on the contract of Platform Integrated Debugging Technical Service. The Offshore drilling company got a total of 2 million yuan of technical services project, which means we had a new breakthrough hard time of low oil price and market downturn.

It is understood that the project includes drilling equipment commissioning, marine equipment commissioning, large-scale experiments and other services. Each of them must meet the specification design requirements.

Zhao Hui believes that the reason why choosing Offshore drilling company as a partner is its strong professional and technical skills of construction specifications and equipment management. During the cooperation between the two sides, our employees showed great responsible for each construction, each equipment debugging accuracy. They carried forward the oil workers’ good characteristics like hard-working, professional, dare to challenge difficulties. But also, Offshore drilling company has brought considerable economic efficiency that contributes to the cooperation.

For the contract of the project, Zhang Jinlong indicated that the company has accumulated a wealth of experience in the installation of equipment selection, maintenance management, comprehensive debugging, and also had trained outstanding technicians via 39 years of offshore drilling construction and platform operation. The platform service team to provide on-site has a wealth of experience, familiar with the platform of various equipment and technical specifications. They can well control the node during construction. The company will firmly establish the spirit of the contract, respect for the two sides, pay attention to safety and environmental protection, strict quality control to create a quality project, quality engineering. Zhang Jinlong showed full of confidence to that.

In recent years, in response to the grim situation of low oil prices, the company promoting offshore drilling industry while taking the initiative to go abroad and enlarge the market, to achieve the transformation form advantages of resources to the benefits of conversion. Dingsheng Jinggong had successively output the technological management team to the Saudi project; cooperated with the Shanghai Petroleum Bureau for the export logging technology services; output technicians to Shanxi, Xinjiang market and so on. The potential of company management, technology, personnel and other superior resources have been further tapped and released. It brought economic benefits and enhanced the company’s viability. The success of this cooperation indicated the new stage of beneficial transformation via outputting management, technology, personnel and other resources.


The first factory drilling platform in the Chad project is completed

China Petroleum Network News (Special correspondent Ding Lei correspondent Wang Xixiong)At 21:50 GMT on February 14th, the surface cementing safety of the Daniela1-16 well ended with the wake of the loudspeaker of the Great Wall Drilling and Cementing Company Chad project engineer, Deng Chunlai. At this moment, the company’s safe and efficient and independent construction completed all surface cementing construction of the first Chad drilling platform Daniela1-14 platform 7 well platforms.

The Daniela1-14 platform is the first drilling platform in Chad to be factory-operated. The platform is drilled and then surface cementing is finished by installing and rigs on the rails at the well site. The implementation of the drilling includes two platforms, constructed by the Great Wall drilling GW58 team and GW59 team.

Due to the short construction period, and two drilling platforms at the same time, Industrial drilling platform shall do a cementing every other day. And also, the Daniela1-14 platform operating site is 100 km far from the base, so there has more difficulty to the cementing team for production organization.

In order not to affect the planed operation, the company has overc0me many difficulties, such as technician shortage at site, vehicle shortages, construction distance and so on. They actively coordinated with the site team, moving team for vehicles. During moving operation, the technicians implemented strictly as per the lifting operation procedures, and accomplished moving and installing the cement vertical ash cans, water tanks, pressure fans, tools, containers and other facilities in place within only 12 hours. All the technicians, engineers and operators all eat and sleep at well site.

For the purpose of ensuring the construction carry on timely and smoothly, all staff of Dingsheng Jinggong takes many measures to provide the best service for the customers by actively communicating with drilling team, timely grasping the drilling platform schedule and deciding cementing plan according to actual production in advance. We transported the cement admixture required for cementing in advance on the basis of increasing the storage capacity of the site cement.

We reasonable arranged production, and did not delay the construction at site. At the same time, we mixed cement at base and timely maintained equipment using the spare time after site construction for the smooth construction. We combined our experience with fully studied parameter of drilling to decide the reasonable quantity of cement to ensure the cement can submerge the surface and overflow too much. We tried our best to cut cost and reduce the amount of waste disposal to protect the environment at the same time.

From February 3 to 15, Dingsheng Jinggong completed the Daniela1-14 platform and the Daniela1-22 platform surface for 10 times within 13 days. All stuff refined their work and realized all wells surface qualified cements. The cement back onto ground within 1 cubic meter which earned precious time for oil drilling. The construction quality of the cementing ground is excellent, and it is the highest record of the unit's single-week workload and output value. It has won the praise of the customer and accumulated valuable experience for the cementing work for the drilling platform in Chad.